by Karthik K | Sep 20, 2019
Project Manager Responsibilities The Project Manager is responsible for the entire project until the appropriate parties (for example the architect, engineers, and client representatives) acknowledge (“sign off”) that all final punch lists are complete. The Project...
by Karthik K | Sep 20, 2019
Test Inspections by Governing Agencies Schedule a pre-final inspection with all governing agencies, including the fire marshal, health department, and environmental agencies. This inspection takes place a minimum of thirty (30) days before project completion, to allow...
by Karthik K | Sep 20, 2019
Demobilize the Job Site The Superintendent is responsible for removing equipment and discontinuing services upon project completion. Demobilization includes performing the following tasks, at a minimum:Discontinue all utilities to the field office and have all...